Scope of Work & Estimate
406 Galveston Ct · Hampton, VA
406 Galveston Ct — kitchen floor
$1,642.50 Estimate — 10% discount applied
406 Galveston Ct · Hampton, VA
10% Customer Discount
View PDF Estimate valid until 09/09/2026
Project Overview
Customer: Charles Quigley
Project: Kitchen Floor Replacement
Address: 406 Galveston Ct, Hampton, VA
Existing floor: Ceramic tile over backer board
New floor: Cork-backed LVP (customer's selection at Floor & Decor)
Cabinets: Stay in place — floor work goes around them
Included Scope
10100General Conditions & Management$150.00
  • Jobsite protection, daily clean-up, debris containment
  • Coordination of the demo, leveling and flooring sequence
10101Ceramic Tile & Backer Board Removal — Kitchen (120 sq ft)$300.00
  • Remove existing ceramic tile and the old backer board down to the subfloor
  • Dust-seal the kitchen and protect adjacent areas during removal
10103Subfloor Leveling — Kitchen (120 sq ft)$300.00
  • Flatten and level the subfloor (floor leveler or plywood as needed)
  • Addresses the low/sagging area under the refrigerator
  • Final method confirmed once the tile is up and the subfloor is exposed
10117Luxury Vinyl Plank — Supply & Install (120 sq ft)$600.00
  • Cork-backed LVP, customer's color selection at Floor & Decor
  • Material allowed at the $2.00/sq ft budget — a higher-priced selection is billed as the difference
  • Professional installation, moisture barrier and underlayment as required
10117Floor Transition Strips (2 doorways)$100.00
  • Transition strips where the new LVP meets the adjacent flooring
10109Shoe Molding / Quarter-Round (30 linear ft)$75.00
  • New shoe molding around the kitchen where the floor meets the baseboard
MISCAppliances — Out & Reset$150.00
  • Refrigerator and dishwasher carefully pulled out for the floor work, then reset in place
  • Dishwasher is moved, not replaced
10101Debris Removal & Haul-Off$150.00
  • Removal and haul-off of the old tile, backer board and job debris
Payment Schedule — 50 / 50
Deposit — to Schedule
50%
$821.25 upon signing
Final — on Completion
50%
$821.25 upon completion
Itemized Estimate
10100 — General Conditions & Management$150.00
10101 — Ceramic Tile & Backer Board Removal (120 sq ft)$300.00
10103 — Subfloor Leveling (120 sq ft)$300.00
10117 — LVP Supply & Install (120 sq ft)$600.00
10117 — Floor Transition Strips (2)$100.00
10109 — Shoe Molding / Quarter-Round (30 lf)$75.00
MISC — Appliances Out & Reset$150.00
10101 — Debris Removal & Haul-Off$150.00
10% Customer Discount−$182.50
GRAND TOTAL$1,642.50
Terms & Conditions

By agreeing to these Terms and Conditions, the customer acknowledges and accepts the outlined responsibilities and scope of work.

Scope: All work described in the Included Scope above. Any work not listed is not included unless agreed in writing.

Not included: Carpet in the other rooms (planned separately — "one floor at a time"), cabinet or countertop replacement, baseboard replacement, painting, plumbing or electrical changes, moving furniture or personal items beyond the refrigerator and dishwasher, and work outside the kitchen.

Contractor supplies: LVP flooring at the $2.00/sq ft budget allowance, floor leveler / plywood, transition strips, shoe molding, fasteners and adhesives. If the LVP the customer selects at Floor & Decor is above the $2.00/sq ft budget, the difference is billed as an adjustment; labor is unchanged.

Notes:
**Jobsite will be left clean once completed.

**Refrigerator and dishwasher are moved and reset by the contractor; the contractor is not responsible for pre-existing appliance conditions.

Warranty:
**12 months workmanship.

Payment Terms:
· Total Project Cost: $1,642.50 (10% customer discount applied — was $1,825.00)
· Deposit to Schedule: $821.25
· Final Payment: $821.25

Check is a preferred method.

Validity: valid until September 9, 2026 (one week from the estimate date).